     2005 Winter

Late Feb to Sunday 20 Mar Ballast delivery for second track, ornamental landscaping, bridge section cut and moved out of way of ballast delivery lorries. Drain work near B&Q (PWay hut). Vegetation cleared from top of big bank. A furry intruder! Pictures below,

 

downline02

 

 

hawkhurstpole02

ornamentalrvr02

 

 

overthefence02

bridgecut02

 

 

ballastbigtime02

nawtypuddy02

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Wednesday 23 Feb update Oak tree sidings worked on during preceding week, straps removed from all exposed bridge sections, and some timbers laid by track for reworking into point sleeper timbers. Trees leaning on Network Rail fence removed.

 oaktree02

 

Sunday 13 Feb Finished tree and high level clearance near first bridge. Crane repaired and tested. Oak Tree sidings tidy up.

February 05 Driver training and work started on foundations for platform ramp for disabled patrons.

30 Jan pictures

A very water a clay clogged trackbed.

clay02

clay102

clay302

clay202

 

 

 

 

 

 

 

 

 

 

 

 

 

22th Jan 05

fuelinup102

fuelinup02

Fuelling up Titan

With all the plant on site, we have been getting through a large quantity of red diesel.

 

 

 

 

 

 

 

 

16th Jan

drain02

dumpndig102

dumpndig02

 

 

 

 

 

 

 

 

 

 

 

 

 

A lot of extra material has gone into Oak Tree sidings and this area is constantly being extended and relandscaped. The crane has kindly been donated to the Rother Valley Railway, as it was expected to cost us money being relocated from the Spa Valley.

 

January 05 Lots of digger and dumper action at the RVR. A new drainage ditch has been constructed along by the bank, from near the workshop container right down past the bridge sections, and partially filled with scrap ballast and also piped. During the excavation work, the original trackbed was exposed near bridge sections, under a load of wealden clay, and an old drain and soakaway, which is still in excellent condition, and is being incorporated into the drainage works. A few manhole covers have to be fabricated and some more work done to finish. Bridge sections still on site as scrap value not back up to level for sale yet, this is holding up finance for trackwork and infrastructure needed to commence brakevan rides - hopefully this situation will change soon. Driver training has commenced.

[Home] [Aspirations] [About Us] [Contact Us] [Financial Aid] [Events] [Stock List] [Updates] [2010 1st Half] [2009 2nd Half] [2009 1st Half] [2008 2nd Half] [2008 1st Half] [2007 2nd Half] [2007 1st Half] [2006 2nd Half] [2006 Winter] [2006 Spring] [2005 Autumn] [2005 Summer] [2005 Spring] [2005 Winter] [2004 2nd Half] [2004 1st Half] [Sales-n-Wants] [Members Area] [Links]